Home Why the Indian Artillery lacks the indigenous Bi Modular Charge System (BMCS)?

Why the Indian Artillery lacks the indigenous Bi Modular Charge System (BMCS)?

The foundation stone of the fortieth Ordnance Factory for manufacture of Bi Modular Charge System(BMCS) for the Indian army’s artillery was laid at Rajgir in Nalanda on April 14, 1999 by the then Prime Minister of India[i]. The factory was expected to be completed by November 2005. Since the sanction of the project, a lot of otherwise grueling positives have happened, which include acquisition of approximately 2,650 acres of land, rehabilitation of 1,191 families[ii] that were displaced, conclusion of contracts for Transfer of Technology (ToT) and construction of manufacturing plants with some of the biggest firms in the world like Denel of South Africa, Israel Military Industries (IMI), Biazzi of Switzerland and Bowas of Austria; after several rounds of tendering[iii].  As on January 01, 2012 the Ordnance Factory Nalanda had on its roll 142 employees[iv] and till May 31, 2014 over Rupees 910 crores have been expended on the project. Despite pressing user demand, commitment of the country’s executive, colossal investment of public money and all the activity, the factory isn’t producing as yet. What makes matters worse is the fact that in response to a recent parliament question, the Government has informed that no time line has been fixed for completion of construction of Ordnance Factory at Nalanda in view of the uncertainties in procurement/fabrication of the BMCS plant[v].

Many have referred to the project as jinxed but on the other hand the story of factory at Nalanda tells all about the pitfalls involved in building indigenous defence capability through the public sector route. Apart from failings in project planning and procedural inadequacies; reaction to corruption, fear of corruption and corruption contribute the most towards system’s failing. An analysis of the activities and decisions taken regarding the factory in past 15 years throws up some very good deductions with respect to our capability accretion process.

The Ordnance Factory Nalanda needs three plants to operationalize. The foremost being the BMCS main plant which constitutes of five sub plants. These include the Combustible Cartridge Case Plant, Single Base Propellant Plant, Triple Base Propellant Plant, Nitro-cellulose/Nitro-glycerin paste Plant and Propellant Charge Assembly Plant. The two secondary plants are those which manufacture primary ingredients - Nitro-glycerin and Nitro-cellulose. Interestingly, these three plants were tendered separately. The project of setting up of the factory was thus effectively converted into three independent and uncoordinated procurement decisions. The current reality is that while the feeder plants are raring to go, the main BMCS plant is nowhere in sight. The feeder plants may even waste out even before the factory sees some real action! Sound Project planning is pivotal to any infrastructure creation.  Things may have been entirely different if the three plants were tendered as a package deal.

The reaction to corruption is next area of concern which needs to be analysed pragmatically. The Army after extensive trials recommended procurement of BMCS from Somchem, a division of Denel, South Africa, in 1998-99. The company was the only known manufacturer of BMCS at that time. A contract was concluded with Denel for procuring 4 lakh BMCS modules in April 2002 along with TOT for indigenous production. The contract envisaged delivery of TOT documents which comprised of product specifications including detailed dimensional drawings and designs, quality and inspection procedures, process descriptions and production methods in respect of raw materials, intermediate products and final products. The total cost of the TOT package was of US $ 13.99 million. Tender Enquiry for construction of the BMCS plant was issued for the first time on March 29, 2004. The technical bids were opened on July 12, 2004 and price bids on October 26, 2004. IMI Israel emerged as the L-1 firm at a cost of Rupees 571.71 crore. However, the Ministry of Defence in June 2005 decided to cancel all contracts with Denel due to allegations of corruptions in some other case. The Nalanda project was also kept in abeyance from June 2005 to July 2006, even though Denel had supplied the necessary ToT documents and payment for it had been made. The decision to hold the project in abeyance as also subsequent delay in finalizing contracts led to considerable cost and time overrun. The estimated cost as per revised sanction increased to Rupees 2,160.51 crore in February 2009 from Rupees 941 crore originally sanctioned. The reaction to corruption in the instant case had no effect on Denel but the army suffered immensely.

After the project was restarted in July 2006, IMI asked for price increase from the originally quoted price of Rupees 571.71 crore to Rupees 654.79 crore. OFB did not accept the increased price and issued fresh global tender enquiry on February 26, 2007 with a view to generate more competition. Out of the five companies to whom tenders were issued, only three responded. Later, only two companies remained in consideration since the third refused to sign the integrity pact. The price bid was opened on 28 January 2008. The offer of IMI Israel was the lowest at Rupees 1,090.83 crore and the next higher quote was at Rupees 1,885 crore. During the earlier negotiations, the escalation demanded by the IMI was 15 per cent over a period of two years from July 2004 to August 2006. Against the fresh tender, the escalation was 67 per cent over a period of one year. Refusal to accept the asking price of Rupees 654.79 crore proved very costly. One actually wonders what prompted retendering, when it was known that firms capable and willing to supply BMCS plant are very few. Playing too safe in almost all cases adds to costs.

The contract for the BMCS plant with IMI Israel was finally concluded in March 2009 at the total cost of Rupees 1,175 crore. Advance amounting to Rupees 174 crore was also paid to IMI, which remained idle as all the transactions with IMI were put on hold in June 2009 by the Ministry of Defence. Finally, corruption took its toll and the contract was cancelled post investigation of allegations relating to illegal gratification. IMI was debarred from doing any further business dealing with Ministry of Defence for a period of ten years.

Having failed to procure the plant it was decided to fabricate the BMCS plant indigenously. Despite claims of competence by DRDO and the OFB the required plants haven’t materialized till date.  Interestingly, DRDO had claimed to have addressed the requirement way back in 2006. To quote from the December 2006 issue of Technology Focus, a bulletin of the DRDO, “DRDO has developed BMCS for 39 caliber 155 mm guns, which can also be used for 45/52 caliber 155 mm guns. … … … Dynamic trials have established that indigenous BMCS are equivalent to imported BMCS in all respects like muzzle velocity and range[vi].”  Currently, a Project Monitoring Board at the level of the Ministry of Defence and a steering committee at the level of the OFB, are in place to monitor the project. Both are unable to indicate a timeline for completion of the project, as on 15 July 2014.

It is very apparent from the case that the public sector entities which form the Indian defence supply chain have failed to procure from foreign manufacturers/indigenously fabricate the BMCS plant. This is despite the fact that the country has purchased the requisite technology to include product specifications, detailed dimensional drawings and designs, quality and inspection procedures, process descriptions and production methods in respect of raw materials, intermediate products and final products. In the last fifteen years we have made repeated attempts to address failings in operationalization of Ordnance Factory at Nalanda by repeating steps of the procedure for capital procurement. It is time for decision makers to stop reinforcing failures. It is time to redefine the Indian army’s supply chain for BMCS. If we fail to exploit the domestic private sector defence industry to execute the project, our state will not change. It is time to privatise or at least corporatise. 

 

Views expressed are personal.

References

[i] Press Information Bureau. (2002, Dec 12). Press Release. Retrieved Aug 14, 2014, from Ordnance Factory at Nalanda: http://pib.nic.in/archieve/lreleng/lyr2002/rdec2002/12122002/r1212200224.html 

[ii] Press Information Bureau. (2010, July 27). Press Information Bureau. Retrieved Aug 14, 2014, from Nalanda Ordnace Factory: http://www.pib.nic.in/newsite/erelease.aspx?relid=63599

[iii] CAG. (2010-11). Procurement of Stores and Machinery in Ordnance Factories, Report No 15 . New Delhi: CAG, Govt of India. All details regarding contracts are from the CAG report.

[iv] Ordnance Factory Project Nalanda. (n.d.). Retrieved Aug 15, 2014, from Ordnance Factory Board: http://ofbindia.gov.in/units/index.php?unit=ofn&page=my_3&lang=en

[v] Press Information Bureau. (2014, Juy 15). Press Information Bureau. Retrieved Aug 14, 2014, from Ordnance Factory Rajgir: http://pib.nic.in/newsite/PrintRelease.aspx?relid=106590

[vi]Armament Technology. (Dec 2006). Technology Focus.

Previous ArticleNext Article
Sanjay Sethi
Former Senior Fellow
Contact at: [email protected]
Share
More Articles by Sanjay S...
Restructuring Management of Defence Valu
# 1335 February 11, 2015
more-btn
Books
  • Surprise, Strategy and 'Vijay': 20 Years of Kargil and Beyond
    Price Rs.930
    View Detail
  • Space Security : Emerging Technologies and Trends
    By Puneet Bhalla
    Price Rs.980
    View Detail
  • Securing India's Borders: Challenge and Policy Options
    By Gautam Das
    Price Rs.
    View Detail
  • China, Japan, and Senkaku Islands: Conflict in the East China Sea Amid an American Shadow
    By Dr Monika Chansoria
    Price Rs.980
    View Detail
  • Increasing Efficiency in Defence Acquisitions in the Army: Training, Staffing and Organisational Initiatives
    By Ganapathy Vanchinathan
    Price Rs.340
    View Detail
  • In Quest of Freedom : The War of 1971
    By Maj Gen Ian Cardozo
    Price Rs.399
    View Detail
  • Changing Demographics in India's Northeast and Its Impact on Security
    By Ashwani Gupta
    Price Rs.Rs.340
    View Detail
  • Creating Best Value Options in Defence Procurement
    By Sanjay Sethi
    Price Rs.Rs.480
    View Detail
  • Brave Men of War: Tales of Valour 1965
    By Lt Col Rohit Agarwal (Retd)
    Price Rs.320
    View Detail
  • 1965 Turning The Tide; How India Won The War
    By Nitin A Gokhale
    Price Rs.320
    View Detail
more-btn